Chinese-built power plants in Uganda to reduce tariff rate by 17.5 pct
                     Source: Xinhua | 2019-05-16 19:00:59 | Editor: huaxia

    Uganda's President Yoweri Museveni (R, back) and Zheng Zhuqiang (L, back), the Chinese ambassador to Uganda, unveil a milestone during an inauguration ceremony in Kayunga, Uganda, March 21, 2019. Uganda's President Yoweri Museveni on Thursday inaugurated the Chinese-built Isimba Hydropower Plant on the Victoria Nile in the central part of the African country. (Xinhua/Zhang Gaiping)

    KAMPALA, May 16 (Xinhua) -- The Ugandan government said here Wednesday that Chinese-constructed Isimba and Karuma hydro power plants will reduce the generation tariff in the east African country by 17.45 percent.

    Once the two power plants are commissioned and the power fully utilized, the generation tariff will reduce from the current 6.47 U.S. cents/kWh to 5.34 cents/kWh, said a statement of Uganda's ministry of energy and mineral development.

    The 183MW Isimba Hydro Power Plant was commissioned in March while the 600MW Karuma Hydro Power Plant is under construction.

    Uganda currently has a total installed generation capacity of 1,202MW, according to the ministry figures.

    Back to Top Close
    Xinhuanet

    Chinese-built power plants in Uganda to reduce tariff rate by 17.5 pct

    Source: Xinhua 2019-05-16 19:00:59

    Uganda's President Yoweri Museveni (R, back) and Zheng Zhuqiang (L, back), the Chinese ambassador to Uganda, unveil a milestone during an inauguration ceremony in Kayunga, Uganda, March 21, 2019. Uganda's President Yoweri Museveni on Thursday inaugurated the Chinese-built Isimba Hydropower Plant on the Victoria Nile in the central part of the African country. (Xinhua/Zhang Gaiping)

    KAMPALA, May 16 (Xinhua) -- The Ugandan government said here Wednesday that Chinese-constructed Isimba and Karuma hydro power plants will reduce the generation tariff in the east African country by 17.45 percent.

    Once the two power plants are commissioned and the power fully utilized, the generation tariff will reduce from the current 6.47 U.S. cents/kWh to 5.34 cents/kWh, said a statement of Uganda's ministry of energy and mineral development.

    The 183MW Isimba Hydro Power Plant was commissioned in March while the 600MW Karuma Hydro Power Plant is under construction.

    Uganda currently has a total installed generation capacity of 1,202MW, according to the ministry figures.

    010020070750000000000000011100001380638781
    主站蜘蛛池模板: 日韩xxxx厕所撒尿视频| 精品国产污污免费网站| 国模gogo大胆高清网站女模| 久久国产精品99精品国产| 99精品无人区乱码1区2区3区 | 国产精品无码MV在线观看| 两根手指就抖成这样了朝俞| 最近免费中文字幕大全| 亚洲综合色7777情网站777| 色偷偷狠狠色综合网| 国产激情视频在线观看首页| 99视频有精品视频免费观看| 成年午夜性视频| 久久精品隔壁老王影院| 欧美精品黑人粗大| 北条麻妃在线一区二区| 香蕉视频在线观看男女| 国产精品欧美亚洲| free性泰国女人hd| 我要看WWW免费看插插视频| 久久精品无码免费不卡| 欧美日韩亚洲国产精品一区二区| 免费黄色一级片| 色中色在线下载| 国产对白国语对白| 1000部啪啪毛片免费看| 处处吻动漫高清在线观看| 中文天堂在线观看| 日本爽爽爽爽爽爽在线观看免| 亚洲一区在线免费观看| 欧美色综合高清视频在线| 制服丝袜自拍偷拍| 色噜噜狠狠狠综合曰曰曰| 国产成人免费片在线观看| 伊人一伊人色综合网| 在线亚洲v日韩v| yy6080一级毛片高清| 成人毛片18女人毛片免费| 久久久精品人妻无码专区不卡| 曰批全过程免费视频免费看| 亚洲午夜精品久久久久久浪潮|