China-Laos railway completes first continuous beam block construction on Mekong River

    Source: Xinhua| 2018-09-22 16:57:02|Editor: Liangyu
    Video PlayerClose

    LAOS-LUANG PRABANG-CHINA-RAILWAY CONSTRUCTION-PROGRESS

    Photo taken on Sept. 21, 2018 shows the Luang Prabang cross-Mekong River super major bridge under construction by the China Railway No.8 Engineering Group (CREC-8) in Luang Prabang, Laos. The concrete casting for the first block of the Luang Prabang cross-Mekong River super major bridge's continuous beam along the China-Laos Railway was completed on Sept. 17, the Chinese contractor told Xinhua on Saturday. (Xinhua/Liu Ailun)

    LUANG PRABANG, Laos, Sept. 21 (Xinhua) -- The concrete casting for the first block of the Luang Prabang cross-Mekong River super major bridge' continuous beam along the China-Laos Railway was completed on Sept. 17, the Chinese contractor told Xinhua on Saturday.

    Yan Haiyong, CPC party secretary of the China Railway No.8 Engineering Group (CREC-8)'s railway project department, who is in charge of the construction of the two bridges across the Mekong along the China-Laos Railway, said that the Luang Prabang railway bridge with a total length of 1458.9 meters, is a key project of the China-Laos Railway.

    According to Yan, the bridge's continuous beam design has high technical standards and is difficult to construct with pier-side bracket. The first block of the continuous beam has a length of 12 meters and consumes a concrete volume of 266 cubic meters.

    The China-Laos Railway starts from the border between China and Laos in northern Laos and ends in Vientiane, the capital of Laos. It is the first overseas railway project to be invested, constructed and operated jointly by the Chinese side and directly connected to the Chinese railway network.

    The China-Laos Railway is 414 km long, of which the bridge is about 62 km long and the tunnel is about 198 km long.

    The China-Lao Railway adopts Chinese technical standards and uses Chinese equipment. It started construction in December 2016. It is scheduled to be completed and open to traffic in December 2021.

    The project is designed, constructed and operated in accordance with Chinese railway standards and has a design operating speed of 160 km per hour.

       1 2 3 Next  

    KEY WORDS: China-Laos
    EXPLORE XINHUANET
    010020070750000000000000011100001374864281
    主站蜘蛛池模板: mm1313亚洲国产精品无码试看 | 国产探花在线观看| 中国性猛交xxxxx免费看| 欧美在线暴力性xxxx| 华人生活自拍区杏吧有你| 99自拍视频在线观看| 夜恋全部国产精品视频| 中文字幕日韩精品在线| 麻豆一二三四区乱码| 夜夜燥天天燥2022| 中文无码av一区二区三区| 欧美人与性动交α欧美精品 | 四虎网站1515hh四虎| 亚洲五月激情网| 外卖员被男顾客gay| 久久99精品久久久久久hb无码 | 国产午夜精品一区二区三区不卡| 91高清完整版在线观看| 怡红院老首页主页入口| 久久国产精品久久精| 欧美日韩一区二区三区麻豆| 免费大香伊蕉在人线国产| 蜜桃视频一区二区| 国产激情无码一区二区三区 | 欧美亚洲国产成人不卡| 伊人五月天婷婷| 美女福利视频一区二区| 国产在线98福利播放视频免费| 18禁止看的免费污网站| 夜爽爽爽爽爽影院| 一道本在线免费视频| 日本三级香港三级人妇99视| 五月婷婷六月天| 欧美性猛交xx免费看| 亚洲综合无码一区二区三区| 精品久久无码中文字幕| 国产a级毛片久久久精品毛片| 黄a视频在线观看| 国产精品久久久久久福利| A国产一区二区免费入口| 忘忧草www日本|